The production supervisor of the Machining Department for Rodriguez Company agre
ID: 2466252 • Letter: T
Question
The production supervisor of the Machining Department for Rodriguez Company agreed to the following monthly static budget for the upcoming year:
The actual amount spent and the actual units produced in the first three months of 2016 in the Machining Department were as follows:
The Machining Department supervisor has been very pleased with this performance because actual expenditures for January–March have been less than the monthly static budget of $480,000. However, the plant manager believes that the budget should not remain fixed for every month but should “flex” or adjust to the volume of work that is produced in the Machining Department. Additional budget information for the Machining Department is as follows:
Part A: Flexible Budget
a. Prepare a flexible budget for the actual units produced for January, February, and March in the Machining Department. Assume depreciation is a fixed cost. If required, use per unit amounts carried out to two decimal places. Enter all amounts as positive numbers.
Feedback
For each level of production, show wages, utilities, and depreciation.
Consider performance and spending.
Learning Objective 2, Learning Objective 4.
Part B: Decision Analysis
b. Compare the flexible budget with the actual expenditures for the first three months. Enter all amounts as positive numbers.
What does this comparison suggest?
Rodriguez CompanyMachining Department
Monthly Production Budget Wages $384,000 Utilities 36,000 Depreciation 60,000 Total $480,000
Explanation / Answer
The comparison suggest that The Machining Department has performed better than originally thought.
January February March Units of production 90,000.00 100,000.00 110,000.00 Wages 288,000.00 320,000.00 352,000.00 Utilities 27,000.00 30,000.00 33,000.00 Depreciation 60,000.00 60,000.00 60,000.00 Total 465,000.00 510,000.00 555,000.00 Supporting calculations: Units of production 90,000.00 100,000.00 110,000.00 Hours per unit 0.20 0.20 0.20 Total hours of production 18,000.00 20,000.00 22,000.00 Wages per hour 16.00 16.00 16.00 Total wages 288,000.00 320,000.00 352,000.00 Total hours of production 18,000.00 20,000.00 22,000.00 Utility costs per hour 1.50 1.50 1.50 Total utilities 27,000.00 30,000.00 33,000.00Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.