Samtech Manufacturing purchased land and building for $4 million. In addition to
ID: 2459433 • Letter: S
Question
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building:
4600
An independent appraisal estimated the fair values of the land and building, if purchased separately, at $4 and $1 million, respectively. Shortly after acquisition, Samtech spent $88,000 to construct a parking lot and $46,000 for landscaping. Samtech demolished the building. Demolition costs were $310,000 and the salvaged materials were sold for $9,000. In addition, Samtech spent $85,000 clearing and grading the land in preparation for the construction of a new building.
What is the initial valuation of the land?
Samtech Manufacturing purchased land and building for $4 million. In addition to the purchase price, Samtech made the following expenditures in connection with the purchase of the land and building:
Explanation / Answer
The Initial valuation of land includes all cost incurred in preparing the land for its intended purpose. That includes
Procurement price = $4 million
+ title insurance = $22000
+ legal fees = $8000
+ state transfer fees = $4600
+ demolition cost less salvage of material= $301000
+ clearing & grading cost= $85000
Total Land cost = $4,420,600