Acme Company’s production budget for August is 18,900 units and includes the fol
ID: 2445425 • Letter: A
Question
Acme Company’s production budget for August is 18,900 units and includes the following component unit costs: direct materials, $7.20; direct labor, $11.40; variable overhead, $5.40. Budgeted fixed overhead is $46,000. Actual production in August was 21,840 units, actual unit component costs incurred during August include direct materials, $9.60; direct labor, $10.80; variable overhead, $6.20. Actual fixed overhead was $48,900, the standard direct material cost per unit consists of 8 pounds of raw material at $0.9 per pound. During August, 262,080 pounds of raw material were used that were purchased at $0.80 per pound.
Required: Calculate the materials price variance and materials usage variance for August. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable.)
Explanation / Answer
Direct Material Price Variance:
= 262,080 x 0.8 - 262,080 x 0.9
= 209,664 - 235,872
= -26,208 U
Direct Material Usage Variance:
= Actual Quantity x Standard Price - Standard Quantity x Standard Price
= 262,080 * 0.9 - 151,200 * 0.9
= 235,872 - 136,080
= 99,792 F
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.