Question

Budget Performance Reports for Cost Centers

Partially completed budget performance reports for Garland Company, a manufacturer of light duty motors, follow:



a. Complete the budget performance reports by determining the correct amounts for the lettered spaces (a-l) as marked above.

b. The budget for the Chip Fabrication Department indicates that the budget overrun was caused by a combination of budget in wages, power and light, and maintenance that exceeded a budget in materials.

Garland Company
Budget Performance Report—Vice President, Production
For the Month Ended November 30
Plant Actual Budget Over Budget Under Budget Eastern Region $549,800 $549,800 $0 Central Region 395,900 391,900 4,000 Western Region (g) (h) (i) $(j) $(k) $(l) $3,170

Explanation / Answer

Answers

Garland Company

Budget Performance Report—Manager, Western Region Plant

For the Month Ended November 30

Department

Actual

Budget

Over Budget

Under Budget

[A]

[B]

[A – B]

[B – A]

Chip Fabrication

$                           105,330.00

$            108,490.00

$                          3,160.00

Electronic Assembly

$                             83,630.00

$               84,720.00

$                          1,090.00

Final Assembly

$                           134,640.00

$             133,560.00

$                       1,080.00

TOTAL

$                           323,600.00

$             326,770.00

$                       1,080.00

$                          4,250.00

Garland Company

Budget Performance Report—Vice President, Production

For the Month Ended November 30

Plant

Actual

Budget

Over Budget

Under Budget

[A]

[B]

[A – B]

[B – A]

Eastern Region

$                           549,800.00

$             549,800.00

$                                    -  

$                                       -  

Central Region

$                           395,900.00

$             391,900.00

$                       4,000.00

Western Region

$                           323,600.00

$             326,770.00

$                          3,170.00

TOTAL

$                       1,269,300.00

$         1,268,470.00

$                       4,000.00

$                          3,170.00

Questions

Answer figure

a.

$                   105,330.00

b.

$                   108,490.00

c.

$                        3,160.00

d.

$                   323,600.00

e.

$                   326,770.00

f.

$                        1,080.00

g.

$                   323,600.00

h.

$                   326,770.00

i.

$                        3,170.00

j.

$               1,269,300.00

k.

$               1,268,470.00

l.

$                        4,000.00

Garland Company

Budget Performance Report—Manager, Western Region Plant

For the Month Ended November 30

Department

Actual

Budget

Over Budget

Under Budget

[A]

[B]

[A – B]

[B – A]

Chip Fabrication

$                           105,330.00

$            108,490.00

$                          3,160.00

Electronic Assembly

$                             83,630.00

$               84,720.00

$                          1,090.00

Final Assembly

$                           134,640.00

$             133,560.00

$                       1,080.00

TOTAL

$                           323,600.00

$             326,770.00

$                       1,080.00

$                          4,250.00