Schurz Corporation\'s management reports that its average delivery cycle time is
ID: 2437381 • Letter: S
Question
Schurz Corporation's management reports that its average delivery cycle time is 27 days, its average throughput time is 10.0 days, its manufacturing cycle efficiency (MCE) is 0.32, its average move time is 0.3 day and its average queue time is 6.0 days Required: a. What is the wait time? (Round your answer to 1 decimal place.) b. What is the process time? (Round your answer to 1 decimal place.) c. What is the inspection time? (Round your intermedliate calculations and finel answer to 1 decimel place.) a. Wait time b. Process time c. Inspection time days days daysExplanation / Answer
Answer a. Delivery cycle time = Wait time + Throughput time 27 Days = Wait Time + 10 Days Wait Time = 27 days - 10 Days Wait Time = 17 days Answer b. MCE = Process time / Throughput time 0.32 = Process Time / 10 Days Process Time = 0.32 X 10 Days Process Time = 3.20 Days Answer c. Throughput time = Process time + Inspection time + Move time + Queue time 10 Days = 3.20 Days + Inspection time + 0.30 Days + 6.00 Days 10 Days = 9.50 Days + Inspection time Inspection time = 10 Days - 9.50 Days Inspection time = 0.50 Days
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.