ro-day-o inc. manufactures belt buckles in a single -step production process. Th
ID: 2435450 • Letter: R
Question
ro-day-o inc. manufactures belt buckles in a single -step production process. The following information is available for june 2010:whole units cost of material cost of labor
beginning work in process 200,000 1,200,000 1,728,000
units started during period 1,000,000 7,800,000 9,612,000
units in ending inventory 300,000
beginning inventory units were 100 percent complete as to material and 80% complete as to labor. The ending inventory units were 100% complete as to material and 50% complete as to labor. overhead is applied to production at the rate of 60% of direct labor cost.
a. prepare a schedule to compute equivalent units of production by cost component assuming the weighted average method.
b. determine the unit production costs for material and conversion.
c. calculate the costs assigned to completed units and ending inventory for august 2010.
Explanation / Answer
a. prepare a schedule to compute equivalent units of production by cost component assuming the weighted average method.
Qty. Schedule
Begining WIP 200,000
Units started 1,000,000
Total units into
Production 1,200,000
Less : Ending WIP 300,000
Transferred to FG 900,000
==========
Equivalent Units
% Materials % Labor
Units Transferred to FG 100 900,000 100 900,000
Ending WIP 100 300,000 50 150,000
Total Equivalent Units 1,200,000 1,050,000
========== ==========
b. determine the unit production costs for material and conversion.
Total Cost DM DL
Beg. WIP $2,928,000 1,200,000 $1,728,000
Process Cost $17,412,000 7,800,000 $9,612,000
Total Cost $20,340,000 9,000,000 $11,340,000
Equivalent Units 1,200,000 1,050,000
Cost per equivalent unit $7.50 $10.80
__________________________________________________________
c. calculate the costs assigned to completed units and ending inventory for august 2010.
Materials Labor Total
Completed units
900,000 x $7.50 $6,750,000
900,000 x $10.80 $9,720,000 16,470,000
Ending WIP
300,000 x $7.50 $2,250,000
150,000 x $10.80 $1,620,000 3,870,000
____________________________________
Total $900,000 $11,340,000 20,340,000
=====================================
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.