Perkins Company, which has a standard cost system, had 500 pounds of raw materia
ID: 2435378 • Letter: P
Question
Perkins Company, which has a standard cost system, had 500 pounds of raw material X in its inventory at June 1, purchased in May for $1.20 per pound and carried at a standard cost of $1.00 per pound.The following information pertains to raw material X for the month of June:
* Actual pounds purchased = 1,400
* Actual pounds used = 1,500
* Standard pounds allowed for actual production = 1,300
* Standard cost per pound = $1.00
* Actual cost per pound = $1.10
The unfavorable materials purchase price variance for raw material X for June was:
1) $ 0.
2) $130.
3) $140.
4) $150.
Explanation / Answer
The formula for calculating the Material price variance is
(Actual price - Standard price) * Actual quantity
According to the given information,
Actual price = $1.10
Standard price = $1.00
Actual quantity is the quantity that is actually purchased but not used.
Actual quantity = 1,400
Substituting the values in the above formula, we get
Direct material price variance = ($1.10 - $1.00) * 1,400
= $0.10 * 1400
= $140
Therefore, the direct material price variance is $140
The correct option is 3) $140
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.