Test:Exam 4/Final Exam Time Remaining: 01:4:02 Submit Test This Question: 1 pt 17 of 35 (4 complete) This Test: 35 pts possible Beaver Company manufactures coffee tables and uses an activity - based costing system. Each coffee table consists of 20 separate parts totaling $180 in direct materials, and requires 5 hours of machine time to produce. Additional information follows Activity Materials handling Machining Assembling Packaging Allocation Base Number of parts Machine hours Number of parts Number of finished units Cost Allocation Rate $4.00 per part $4.20 per machine hour $1.00 per part S2.00 per finished unit What is the cost of materials handing per coffee table? OA. $10 ??, s80 O D. $20 Click to select your answer ??Explanation / Answer
Ans: D.$20
Explanation:
Cost of materials handling per coffee table:
= 20 parts x Rs.1 per part = $20
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.