Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Cutting Department Production Data—July Plant 1 T12-Tables Plant 2 C10-Chairs Co

ID: 2431025 • Letter: C

Question

Cutting Department

Production Data—July

Plant 1
T12-Tables

Plant 2
C10-Chairs

Cost Data—July

T12 Tables

C10 Chairs

LINK TO TEXT

LINK TO TEXT

Materials

Conversion Costs

LINK TO TEXT

LINK TO TEXT

Materials

Conversion Costs

Total Costs

LINK TO TEXT

LINK TO TEXT

T12 Tables

Costs accounted for:

   Transferred out

   Work in process

      Materials

      Conversion costs

         Total costs

C10 Chairs

Costs accounted for:

   Transferred out

   Work in process

      Materials

      Conversion costs

         Total costs

LINK TO TEXT

LINK TO TEXT

THAKIN INDUSTRIES INC.
Cutting Department—Plant 1
Production Cost Report
For the Month Ended July 31, 2017

Equivalent Units

Quantities

Physical
Units


Materials

Conversion
Costs


Costs


Materials

Conversion
Costs


Total

Cost Reconciliation Schedule

Thakin Industries Inc. manufactures dorm furniture in separate processes. In each process, materials are entered at the beginning, and conversion costs are incurred uniformly. Production and cost data for the first process in making two products in two different manufacturing plants are as follows.

Cutting Department

Production Data—July

Plant 1
T12-Tables

Plant 2
C10-Chairs

Work in process units, July 1 0 0 Units started into production 19,500 17,500 Work in process units, July 31 3,100 700 Work in process percent complete 60 80

Cost Data—July

Work in process, July 1 $0 $0 Materials 390,000 280,000 Labor 234,700 113,000 Overhead 112,240 112,680    Total $736,940 $505,680

Explanation / Answer

Ans- For Each Plant:

Physical units of production

T12 Tables C10 Chairs

Units to be accounted for 19,500 17,500

2- Equivalent units of production for materials and for conversion cost

Materials Conversion Costs

T12 Tables 19,500 18,260

C10 Chairs 17,500 17,360

Calculation for Equivalent units of production for conversion cost:

T12-Tables C10-Chairs

Units started into production 19,500 17,500

Work in process units,31 july 3,100 700

Units completed during the year (19,500-3100) 16,400 16,800

(17,500-700)

Work in process percent complete 60 80

Equivalent Units=Units completed+(units in ending inventory*percent complete)

T12-Tables =16,400+3100*60%= 18,260

C10-Chairs= 16,800+700*80%= 17,360

3-The unit costs of production;

Materials Conversion Costs Total costs

Units costs T12Tables $20 $19 $39

(390,000/19,500) ( 234,000+112,240

=346,940/18,260)  

Units costs C10Chairs $16 $13 $29

(280,000/17,500) (113,000+112,680

=225,680/17,360)

4-Costs to units transferred out and in process :

T12 Tables

Costs accounted for:

Transferred out (16,400units * $39total costs) $639,600

Work in process

Materials (3,100* $20 materials unit costs) $62,000

Conversion cost(18,260-16400=1,860* $19

conversion units costs) $35,340 97,340

Total costs $ 736,940

C10 Chairs   

Costs accounted for:

Transferred Out (16,800units*$29 total cost) $487,200

Work in process

Materials(700units *$16 materials unit cost ) $11,200

Conversion costs (17,360-16,800=560*$13

conversion unit cost) $7,280 18,480

Total costs $505,680

5-Production Cost Report:

THAKIN INDUSTRIES INC.

Cutting Department -Plant 1

Production Cost Report

For the Month Ended July 31, 2017

Equivalent Units

Physical Units Materials Conversion Costs

Quantities

Units to be accounted for

Work in process July1

Started into production 19,500

Total Units 19,500

Units accounted for

Transferred out 16,400 16,400 16,400

Work in process July 31 3,100 3,100 1,860

Total Units 19,500 19,500 18,260   

Costs Materials Conversion costs Total   

Units Costs

Total Costs $ 390,000 $346,940 $736,940  

Equivalent units 19,500 18,260

Units costs $20 $19 $39

Costs to be accounted for

Work in process July 1

Started into production $736,940

Total costs $736,940   

Cost Reconciliation Schedule

Costs accounted for

Transferred Out $639,600

Work in process July 31

Materials $62,000

Conversion Costs $35,340 97,340

Total Costs $736,940

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote