2) 2) Lakeside Inc. manufactures four lines of remote control boats and uses act

ID: 2420564 • Letter: 2

Question

2)

2)

Lakeside Inc. manufactures four lines of remote control boats and uses activity-based costing to calculate product cost.

  

  Activity Cost Pool

Estimated
Total Cost

Estimated Cost Driver

  Machining

$

332,000  

13,400

machine hours

  Setup

71,000

450

batches

  Quality control

94,000

790

inspections

  

Suppose the Speedy boat requires 2,000 machine hours, 90 batches, and 320 inspections. Using the activity rates, determine the amount of overhead assigned to the Speedy product line. (Round intermediate calculations to 2 decimal places and your final answers to the nearest dollar amount.)

  

Cost Pool

Allocate Overhead

Machining

Setup Costs

QUALITY CONTROL

Total Overhead

Lakeside Inc. manufactures four lines of remote control boats and uses activity-based costing to calculate product cost.

Explanation / Answer

Solution:

Overhead Allocation / Caluculation Formula:

Cost Pool

Allocate Overhead

Machining

($ 3,32,000 / 2,000) = 166

Setup Costs

($ 71,000 / 90) = 788.88

QUALITY CONTROL

($ 94,000 / 320) = 293.75

Total Overhead

   = 1,248.63

Estimated Cost Drivers Allocation:

Machining = 13,400 / 2,000 = 6.7

Setup = 450 / 90 = 5

QUALITY CONTROL = 790 / 320 = 2.468

Overhead Allocation = Cost Pool / Activity Cost rate measure