24. Activity-Based Costing Bugsy Corp. has the following historical data for ove
ID: 2406037 • Letter: 2
Question
24. Activity-Based Costing Bugsy Corp. has the following historical data for overhead from the past year Human Resources: Information Technology Power Cost S 80,000 30,000 250,000 Activity Driver 1,000 employees 2,000 computers 25,000 kilowatt hours Job # l is expected to use 5 employees, 5 computers, and 2,000 kilowatt hours. a. What is the RATE used to apply HR overhead? ANSWER: b. What is the RATE used to apply IT overhead? ANSWER: c. What is the RATE used to apply Power overhead? ANSWER: d. How much total overhead in dollars should be applied to Job # 1? ANSWER:Explanation / Answer
Solution:
a. Rate used to apply HR overhead = HR cost ÷ number of employees
= $80,000 ÷ 1,000
= $80 per employee
b. Rate used to apply IT overhead = IT cost ÷ number of computers
= $30,000 ÷ 2,000
= $15 per computer
c. Rate used to apply Power overhead = Power cost ÷ number of Kilowatts hours
= $250,000 ÷ 25,000
= $10 per kilowatt hour
d. Total overhead applied to Job 1 = 5 x$80 + 5 x $15 + 2000 x $10
= $20,475
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.