The auto repair shop of Quality Motor Company uses standards to control the labor time and labor cost in the shop. The standard labor cost for a motor tune-up is given below:

Standard hours: 1.5 Standard Rate: 6.00 Standard Cost: 9.00

The record showing the time spent in the shop last week on motor tune-ups has been misplaced. However, the shop supervisor recalls that 150 tune-ups were completed during the week, and the controller recalls the following variance data relating to tune-ups:

Labor rate variance: 306 F Labor Spending variance: 1404 U

1. Determine the actual number of hours spend on tune ups in the week

2. Determine the actual hourly rate of pay for the tune ups

Explanation / Answer

Labor efficiency variance = 1404+306= 1710 U 1 Labor efficiency variance = SR*(AH-SH) 1710 = 6*(Ah-150*1.5) 285 = AH-225 AH = 285+225= 510 hours Actual number of hours = 510 2 Labor rate variance = AH*(SR-AR) 306 = 510*(6-AR) 0.6 = 6-AR AR = 5.4 Actual hourly rate of pay = $5.4