On February 1, 2018, Arrow Construction Company entered into a three-year constr

ID: 2392364 • Letter: O

Question

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,540,000. During 2018, costs of $2,180,000 were incurred with estimated costs of $4,180,000 yet to be incurred. Billings of $2,680,000 were sent, and cash collected was $2,430,000.

In 2019, costs incurred were $2,680,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,930,000 and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of $3,980,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.

Required:
1. Compute the amount of revenue and gross profit or loss to be recognized in 2018, 2019, and 2020 using the percentage of completion method?
2a. Prepare journal entries for 2018 to record the transactions described (credit "various accounts" for construction costs incurred).
2b. Prepare journal entries for 2019 to record the transactions described (credit "various accounts" for construction costs incurred).
3a. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018.
3b. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2019.

Also, What is construction expenses to date for 2019?

Explanation / Answer

2927233

(8,540,000 * 34.2767 %)

4754227

(8,540,000 * 55.6701%)

Percentages of completion Choose numerator ÷ Choose denominator = % complete to date 2018 2180000 ÷ 6360000 = 34.2767 % 2019 4860000 ÷ 8730000 = 55.6701 % 2020 100%