Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

NPV profiles: timing differences An oil drilling company must choose between two

ID: 2382353 • Letter: N

Question

NPV profiles: timing differences

An oil drilling company must choose between two mutually exclusive extraction projects, and each costs $12.4 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t = 1 of $14.88 million. Under Plan B, cash flows would be $2.2034 million per year for 20 years. The firm's WACC is 11.9%.

Construct NPV profiles for Plans A and B. Round your answers to two decimal places. Enter your answers in millions. For example, an answer of $10,550,000 should be entered as 10.55.



Identify each project's IRR. Round your answers to two decimal places.
Project A  %
Project B  %

Find the crossover rate. Round your answer to two decimal places.
%

Is it logical to assume that the firm would take on all available independent, average-risk projects with returns greater than 11.9%?
-Select-yesnoItem 18

If all available projects with returns greater than 11.9% have been undertaken, does this mean that cash flows from past investments have an opportunity cost of only 11.9%, because all the company can do with these cash flows is to replace money that has a cost of 11.9%?
-Select-yesnoItem 19

Does this imply that the WACC is the correct reinvestment rate assumption for a project's cash flows?
-Select-yesno

Discount Rate NPV Plan A NPV Plan B 0% $    million $    million 5 $    million $    million 10 $    million $    million 12 $    million $    million 15 $    million $    million 17 $    million $    million 20 $    million $    million

Explanation / Answer

Plan A IRR = 20%

Plan B IRR = 17%

Yes, firm can take the projects with returns greater than 11.9%.

WACC is the rate which a project should derive in order to be viable. Hence, it is the minimum cost that a project should earn.So, we it can be called a reinvestment rate as this is what a firm must earn in order to honour the stakeholders.So, it is essentially a parameter that a return should justify.

Initial Investment 12400000 WACC 11.9%