Problem Seven Controller Tri Nuygen is analyzing the direct material and direct
ID: 2380912 • Letter: P
Question
Problem Seven
Controller Tri Nuygen is analyzing the direct material and direct labor variances for June. The following information comes from the accounting records. The product is a reinforcement bar used in construction.
Direct material cost for 575,000 lbs of material
$172,500
Pounds used in production
550,000 lbs
Direct labor costs for 230,000 hours
$4,140,000
Units produced
900,000
The standard cost for one bar is:
Direct materials: 0.5 lbs at $0.25 per lb
Direct labor 0.25 hours at $20 per hour
Required: Calculate (a) the direct-material price variance, the (b) direct-material quantity variance, (c) the direct-labor rate variance, and (d) the direct-labor efficiency variance.
Compute the following variances for June, and tell if they are favorable or unfavorable.
Amount Favorable/unfavorable
(a) Direct-material price variance ____________________ __________________
(b) Direct-material quantity variance ____________________ __________________
(c) Direct-labor rate variance ____________________ __________________
Direct material cost for 575,000 lbs of material
$172,500
Pounds used in production
550,000 lbs
Direct labor costs for 230,000 hours
$4,140,000
Units produced
900,000
The standard cost for one bar is:
Direct materials: 0.5 lbs at $0.25 per lb
Direct labor 0.25 hours at $20 per hour
Controller Tri Nuygen is analyzing the direct material and direct labor variances for June. The following information comes from the accounting records. The product is a reinforcement bar used in construction. Required: Calculate (a) the direct-material price variance, the (b) direct-material quantity (c) the direct-labor rate variance, and (d) the direct-labor efficiency variance. Compute the following variances for June, and tell if they are favorable or unfavorable.Explanation / Answer
Hi,
Please find the answer as follows:
Direct Material Price Variance = Actual Quantity of Material Purchased *(Actual Rate - Standard Rate) = 575000*(172500/575000 - .25) = 28750 (Uunfavorable)
Direct Material Quantity Variance = Standard Rate*(Actual Quantity of Material Used - Standard Quantity of Material Used for Actual Production) = .25*(550000 - .5*900000) = 25000 (Unfavorable)
Labor Rate Variance = Actual Hours *(Actual Rate - Standard Rate) = 230000*(4140000/230000 - 20) = 460000 (Favorable)
Labor Efficiency Variance = Standard Rate*(Actual Hours - Standard Hours) = 20*(230000 - 900000*.25) = 100000 (Unfavorable)
Thanks.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.