Job 434 was recently completed. The following data have been recorded on its job
ID: 2377748 • Letter: J
Question
Job 434 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 47,000 Direct labor-hours 630 labor-hours Direct labor wage rate $ 13 per labor-hour Machine-hours 370 machine-hours Number of units completed 3,500 units The company applies manufacturing overhead on the basis of machine-hours. The predeterminedoverhead rate is $11 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2 decimal places. Omit the "$" sign in your response.) Unit product cost $
Job 434 was recently completed. The following data have been recorded on its job cost sheet:
Explanation / Answer
Add: Cost of goods manufactured Direct Materials $ 45,000.00 Direct Labor (630 hrs*$13 per hr) $ 8,190.00 Applied MOH (390 MH * $12.00 per MH) $ 4,680.00 Ending finished goods sold $ 57,870.00 3000 Units produced ($57,870/3000) $ 19.29
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.