The following are the cash flows of two projects: Year Project A Project B 0 ?$3
ID: 2366151 • Letter: T
Question
The following are the cash flows of two projects: Year Project A Project B 0 ?$300 ?$300 1 180 200 2 180 200 3 180 200 4 180 -------------------------------------------------------------------------------- a. Calculate the NPV for both projects if the discount rate is 12%? (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project NPV A $ B -------------------------------------------------------------------------------- b. Suppose that you can choose only one of these projects. Which would you choose? Project A Project BExplanation / Answer
NPV of project A = 300 + 180/1.12 + 180/1.12^2 + 180/1.12^3 + 180/1.12^4 = 846.72 and NPV of project B = 300 + 200/1.12 + 200/1.12^2 + 200/1.12^3 = 780.36 so we will choose project A
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.