The following volume of soil and rock is to be removed from a highway cut: Soil
ID: 1920758 • Letter: T
Question
The following volume of soil and rock is to be removed from a highway cut: Soil 13,000 yd3 of silt and 17,000 yd3 of silty clay; rock, 18,000 yd3 of limestone and 15,000 yd3 of hard shale. The shrinkage factor for the silt is 8% and for the silty clay it is 12%; the swell factor for the limestone is 19% and for the hard shale 9%. a. What will be the volume of the fill constructed form these materials? What is the overall volume change in cubic yards and percent? b. If the volume of the fill is designed to be 58,000 yd3, what would be the needed volume of offsite rock disposal? Next, assuming the rock dumped offsite would be shale, how much volume does this represent in the cut section?Explanation / Answer
new volume of construction work = 13000*0.92 + 17000*0.88 + 18000*1.19 + 15000*1.09 = 64690 yd3
volume change =64690 -(13000+17000+18000+15000) = 1690 yd3
% change = 1690*100/63000 =2.68 %
offsite disposal = 64690-58000=6690 yd3
assuming 6690 yd3 shale has been disposed
as it is shale swell factor is 9%
x*1.09=6690
it represent 6690/1.09 yd3 = 6137 yd3 of soil cut
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.