You have been given the responsibility of picking a steam turbine for an electri
ID: 1858718 • Letter: Y
Question
You have been given the responsibility of picking a steam
turbine for an electrical generation station that is to produce
300MW of electrical power that will sell for $0.05 per
kilowatt-hour. The boiler will produce steam at 700 psia and 700 °F,
and the condenser is planned to operate at 80 °F. The cost of
generating and condensing the steam is $0.01 per kilowatt-hour of
electricity produced. You have narrowed your selection to the three
turbines in the table below. Your criterion for selection is to pay
for the equipment as quickly as possible. Which turbine should you
choose?
Turbine ; Capacity (MW) ; ? ; Cost ($Million) ; Operating Cost
($/kWh)
A; 50 ; 0.9 ; 5 ; 0.01
B; 100 ; 0.92; 11; 0.01
C; 100 ; 0.93; 10.5; 0.015
Need full step by step
Explanation / Answer
Since the problem is based on a 300 MW plant, you will have to adjust costs in terms of the number of units since that will determine total capital costs.
You know for each turbine what the gross income can be based on the selling price of $.05 per KWH and the efficie With the operating costs of $.01and $.015 per KWH you can then determine the net income. By dividing the net income per day by the capital cost you can determine which will give you back the cost of the unit the fastest. Since the income and costs are based on the power generated, the efficiency of the various units is built into the costs and it no long a factor in the calculation.
What is not clear is the items that make up the operating costs. Does it include any taxes or other costs that might be charged against the unit? If it doesn't then this would be called a "before taxes payout or payback.."