nice, be clear and organized Which dispute resolution technique has elements of
ID: 1844465 • Letter: N
Question
nice, be clear and organized
Which dispute resolution technique has elements of both negotiation and arbitration? How can the Owner protect himself in the event of delays from the Contractor? What does the answer to (a) mean to the Contractor? List 2 exceptions to the answer to (a). What percentage of the Building Codes is attributed to Safety? is a written confirmation that the contractor has substantially completed the project. Who verifies it? Who approves it? When does 'Statute of limitation' on defective construction commence? The members of the Dispute Review Board are selected by the American Arbitration Association. True or False. is the most expensive dispute resolution technique. What is the criterion for determining Substantial Completion? Liquidated damages are typically used to penalize the contractor for late completion. True or False. List 3 ways by which a contracter can avoid liquidated damages.Explanation / Answer
1.Neutral fact-finding is the dispute revolution tecnique that has both negotiation and arbitration
2. a)The contractor shall be entitled with extra compensation or extension of time or both.
b) The contractor takes full responsibility for the work.the contractor shall be repsonsible for the damage or destruction of the work. The engineer shall issue to thecontractor a certificate of partial completion or delay and any time the owner may take over and use the permanent construction described in the certificate and may exclude the contractor thereon.
c) The owner may any time suspend the work by giving notice to the contractor in writing. The work shall be resumed by the contractor within ten days after the date is fixed in the written notice from the owner to the contractor.
3. Modern building codes reduced the severity (cost) of insurance losses by 42 percent and the frequency (number) of insured losses by 60 percent.
4. a. Upon receipt of written notice the work is substantially completed or ready for the final inspection and acceptance.
b. The engineer will promptly make an inspection and approves it and architect on the basis of inspection.
c. The engineer promptly issues a certificate over his signature.
5. A statute of limitations normally governs the time within which legal proceedings must be commenced after the cause of action accrues.
6. True
7. Colloborative law is the most expensive dispute resolution technique
8. When the contractor determines the work acceptable to the owner is substantially complete, the contarctor shall prepare for the construction manager for submission to the architect of the list of items to be completed or corrected. the failure to include any items of the list do not alter the responsibility of the contractor to complete all the work in accordance to the contract documents.when Architect on the basis of inspection determines that the work is substantially complete, he will then prepare a certificate of Substantial completion.
9. a) False
b) i. by claiming a head of general damages for the breach of any other provision
ii. For risk evaluation and management purposes, a copy of the prime contract should be obtained and reviewed so any liquidated damages provisions are known at a project
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.