1-when planning or scheduling a project the superintendent and the project manag
ID: 1758411 • Letter: 1
Question
1-when planning or scheduling a project the superintendent and the project manager should look for opportunities to speed up the project by using over time
true or false
2- most construction people dislike meetings, but well-run meetings are essential means of communication on a project and the project manager must make sure that meetings are held regularly and that they are effective
true or false
3- which of the following is NOT a step in planning the project?
a- breaking the job down into subtasks
B- ESTABLISHING THE SEQUENCE OF WORK
c- appointing the project team members
3-most project managers and superintendents break a project down into specific elements and tasks as a normal part of their managerial technique
true or false
4- which level of detail in schedule woul a corporate vice president typically want to see ?
a- high level of detail
b- low level of detail
c- intermediate level of detail
d none of the above
5- each subcontractors activities should always be separate from the other subcontractors so that t responsibility can be assigned should delays to the project occur
true ot false
6- the construction drawing and specifications are the best sources of information to use to start the process of breaking the project down into tasks
true or false
Explanation / Answer
1. FALSE
During planning phase of a project , the project manager should not consider the over time. However he needs to consider over time to speed up the work if the project runs behind the schedule while the project is going on.
2. TRUE
3. C-appointing the project team members
4. a-high level of detail
5. TRUE
6. TRUE