The city is expanding and is in need of a second fire station closer to the newe
ID: 1712035 • Letter: T
Question
The city is expanding and is in need of a second fire station closer to the newer areas of the city to ensure shorter response times. The project manager and the project team have been selected for the project. The team is very interested in selecting the scheduling technique that will be used to follow the project through to completion. The project manager, city manager, and chief of the fire department have set the following criteria for the process of selecting the scheduling technique: easy to use, shows durations of tasks, shows milestones, can see the flow of work, can see the sequence of events, can depict which tasks can be undertaken at the same time, and tell how far tasks are from completion. The city manager favors the Gantt chart, the chief likes PERT, and the project manager prefers CPM.
If you were the project manager, which method would you use, and why?
this is a discussion question
Explanation / Answer
As a project manager i would prefer CPM as there is already a fire station over there another one is yet to come so there is no uncertainity in the upcoming activity.
Based upon our previous experience We can determine which activity is going to be most crtical.
Also it is easier to use and cover all the requirment mention in the problem