Each Activity, other than the first, must have a: a. duration greater than 5 tim
ID: 1710255 • Letter: E
Question
Each Activity, other than the first, must have a: a. duration greater than 5 time units b. predecessor c. successor d. 3 or more assigned resources e. a cost greater than zero Each Activity, other than the last, must have a: a. duration greater than 5 time units b. predecessor c. successor d. 3 or more assigned resources e. a cost greater than zero An Update to a CPM should include and requires for purposes of calculation the following information: a. actual cost to date for activities started b. actual start date for activities started c. remaining duration for activities started d. a, b, and c e. b and c Changing the original duration of an activity is proper during a: a. update of the CPM b. revision of the CPM c. preparing a report for the owner d. preparing a report for the subcontractor e. all of the above If told a subcontractor will leave the job for two weeks and then return to finish five days work, this should be entered into the CPM via a: a. update of the CPM b. revision of the CPM c. change order of the CPM d. delay claim of the CPM e. rebaselining of the CPMExplanation / Answer
Q7 - b, since 1st acivity does not have predecessor
Q8 - c, since last activity does not have a sucessor
Q9 - e, since CPM is all about time, a can be excluded.
Q10 - a,
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.