Earthwork and compaction project: The fill for an embankment of a large industrial facility consists of borrow soil available from a nearby hilly terrain. The borrow sail water content of 7%. Assume the following data for adding water in the fill and compaction. The highway embankmant is to be constructed at the rate of 200 c y/h compacted. a) How many gallons of water must be supplied each hour to increase the water content of the fill soil from 7% in place to 12% optimum condition for compaction? b) How many water tank per hour are needed this job assuming each water tank has 1, 000 gallons maximum capacity? A typical water tank cycle consists of is minutes filling water, 12 minutes having and 8 minutes return time, 20 minutes water spraying time. Assume ss-min/hr efficiency. c) If the compactable fill becomes saturated at a constant volume, what will be its water content? The specified compaction of 90% requires a dry unit weight of 107.4 |b| compacted cubic foot. The specific gravity of soil solid is 2.66.Explanation / Answer
Using the phase relationships the additional amount of water required is found to be 242 galoons which is nearly equal to 968 litres
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.