4 Year Project Mid-Year Factors Project Year Constant Dollars (2.55%) Current Do

ID: 1247691 • Letter: 4

Question

4 Year Project

Mid-Year Factors

Project

Year

Constant Dollars (2.55%)

Current Dollars (4.90%)

1

0.9875

0.9764

2

0.9629

0.9308

3

0.9390

0.8873

4

0.9156

0.8458

Alternative

Project

Total Cost

Discount Factor

Present Value of

Year

Constant FY $

Type

Value

Annual Cost

1

$174,000.00

MOY

0.9875

$171,825.00

2

$174,000.00

MOY

0.9629

$167,544.60

3

$174,000.00

MOY

0.9390

$163,386.00

4

$174,000.00

MOY

0.9156

$159,314.40

Total

$696,000.00

NPV =

$662,070.00

4 Year Project

Mid-Year Factors

Project

Year

Constant Dollars (2.55%)

Current Dollars (4.90%)

1

0.9875

0.9764

2

0.9629

0.9308

3

0.9390

0.8873

4

0.9156

0.8458

Explanation / Answer

Yes, your calculations are perfect. Hence, Option D is the correct answer.