Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Teloxy Engineering has received a one-time contract to design and build 10,000 u

ID: 1185007 • Letter: T

Question

Teloxy Engineering has received a one-time contract to design and build 10,000 units of a new product. During the proposal process, management felt that the new product could be designed and manufactured at a low cost. One of the ingredients necessary to build the product was a small components plus scrap. During the design stage, your engineering team informs you that the final design will require a somewhat higher-grade component that sells for $72 with quantity discounts. The new price is substantially higher than you had budgeted for. This will create a cost overrun. You meet with your manufacturing team to see if they can manufacture the component at a cheaper price than buying it from the outside. Your manufacturing team informs you that they can produce a maximum of 10,000 and the raw material cost is $40 per component. Since Teloxy has never manufactured this product before, manufacturing expects the following defects: All defective parts must be removed and repaired at a cost of $120 per part. Using expected value, is it economically better to make or buy the component? Strategically thinking, why might management opt for other than the most economical choice? your manufacturing team informs you that they have found a way to increase the size of the manufacturing run from 10,000 to 18,000 units in increments of 2000 units. However, the setup cost will be $150,000 rather than $100,000 for all production runs greater than 10,000 units and defects will cost the same $120 for removal and repair. Calculate the economic feasibility of make or buy. Should the probability of defects change if we produce 18,000 units as opposed to 10,000 units? Would your answer to question 1 change if Teloxy management believes that follow-on contracts will be forthcoming? What would happen if the probability of defects changes to 15 percent, 25 percent, and 5 percent due to learning-curve efficiencies?

Explanation / Answer

1) cost of production = $(100000+40*10000)

cost/parts = total cost/10000 = $50

Now, considering defects parts cost

since each defective parts needs to be replaced with cost of $120

so, total cost = 228000

adding this to cost of production, we get

Production cost/parts= 728000/10000= $72.8

Market value /parts = $72

Thus its economically better to buy the component

B)

1)economic feasibility depends upon the return on investment(roi) which is given by

ROI = Present Value Of Benefits / Present Value Of Costs

if the roi is higher,more the process is economical feasible and vice versa

i think in this case it is not economically feasible because the value of cost is higher than the benefits range

2)yes the probability of defects will change as it depends upon the number of products.so as it increases the probabilty increases.

3)yes the economic feasibility could change ina positive way if the contract goes bigger as their is more chance of getting higher rate of return on each component.so it will change.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote