The approximate external rate of return is approximation because a) all net savi
ID: 1165627 • Letter: T
Question
The approximate external rate of return is approximation because
a) all net savings earned by a project are assumed to be invested at the MARR
b) all receipts that occur when a project balance is negative are assumed to be invested at the MARR
c) all receipts are assumed to be invested at the MARR
d) it can be computed only as a trial ERR
a) all net savings earned by a project are assumed to be invested at the MARR
b) all receipts that occur when a project balance is negative are assumed to be invested at the MARR
c) all receipts are assumed to be invested at the MARR
d) it can be computed only as a trial ERR
Explanation / Answer
ERR is the rate of return which makes PW of Costs equal to FW of Revenue and if ERR is less than MARR then we cannot proceed with this project.
In this case all net savings that is (Revenue-Cost) is assumed to be invested at the MARR
Hence option A is correct response here
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.