Queueing Theory a. Parts arrive for processing at a bottleneck tool at an averag

ID: 670563 • Letter: Q

Question

Queueing Theory

a. Parts arrive for processing at a bottleneck tool at an average rate of 15 per hour. The tool processes a part in 3.75 minutes, on average, with a standard deviation of 1.3 minutes.

What is the average number of parts waiting for processing at this bottleneck station? Show all your work.

b. A tool crib that serves a large group of mechanics has exponential inter-arrival and service times. The mean time between arrivals is 3.5 minutes, and it takes 3 minutes on the average for a single tool-crib attendant to provide service to each mechanic. The tool crib attendant is paid $15/hour, and each mechanic is paid $25/hour. Turn in answers to the following questions (show all your work):

i. What is the utilization of the tool crib attendant?

ii. What is the hourly cost at the tool crib?

Explanation / Answer

Data Tabulated first:

Hours

Arrival of parts per hour = 15

tool capacity in minutes

standard deviation = 1.3 minutes

1

15

50.55

34.82501

2

30

101.1

70.56926

3

45

151.65

106.3135

4

60

202.2

142.0578

5

75

252.75

177.802

6

90

303.3

213.5462

7

105

353.85

249.2905

8

120

404.4

285.0347

9

135

454.95

320.779

10

150

505.5

356.5232

11

165

556.05

392.2675

12

180

606.6

428.0117

13

195

657.15

463.756

14

210

707.7

499.5002

15

225

758.25

535.2445

16

240

808.8

570.9887

17

255

859.35

606.733

18

270

909.9

642.4772

19

285

960.45

678.2215

20

300

1011

713.9657

Now to find the answer:

(a) The average number of parts waiting for processing:

Hour

Average Number of parts waiting for processing

Tool Capacity in Hours

1

-187.2

0.8425

2

-172.2

1.685

3

-157.2

2.5275

4

-142.2

3.37

5

-127.2

4.2125

6

-112.2

5.055

7

-97.2

5.8975

8

-82.2

6.74

9

-67.2

7.5825

10

-52.2

8.425

11

-37.2

9.2675

12

-22.2

10.11

13

-7.2

10.9525

14

7.8

11.795

15

22.8

12.6375

16

37.8

13.48

17

52.8

14.3225

18

67.8

15.165

19

82.8

16.0075

20

97.8

16.85

Tool Crib: ( A simulation of 20 arrivals in the Queue):

Arrivals

Arrival Times in minutes

1

0

2

3.5

3

7

4

10.5

5

14

6

17.5

7

21

8

24.5

9

28

10

31.5

11

35

12

38.5

13

42

14

45.5

15

49

16

52.5

17

56

18

59.5

19

63

20

66.5

Time taken by Attendant to delegate(Provide service to) Mechanic (in minutes)

3

6

9

12

15

18

21

24

27

30

33

36

39

42

45

48

51

54

57

60

Hours

Arrival of parts per hour = 15

tool capacity in minutes

standard deviation = 1.3 minutes

1

15

50.55

34.82501

2

30

101.1

70.56926

3

45

151.65

106.3135

4

60

202.2

142.0578

5

75

252.75

177.802

6

90

303.3

213.5462

7

105

353.85

249.2905

8

120

404.4

285.0347

9

135

454.95

320.779

10

150

505.5

356.5232

11

165

556.05

392.2675

12

180

606.6

428.0117

13

195

657.15

463.756

14

210

707.7

499.5002

15

225

758.25

535.2445

16

240

808.8

570.9887

17

255

859.35

606.733

18

270

909.9

642.4772

19

285

960.45

678.2215

20

300

1011

713.9657