PHASE II (30 points total)—Due Week 5 Now that you have completed your first maj
ID: 667128 • Letter: P
Question
PHASE II (30 points total)—Due Week 5
Now that you have completed your first major deliverable in the project, let us move on to the next phase in the project. You need to plan to implement the network. You will configure the switches first.
Task 1: Configure SW1. (3.5 points possible)
Configuration Task
Required Information
Points
Switch name
SW1
¼
Secret Password
Netw204
¼
Disable DNS lookup
¼
Username and Password
User= Admin1, Password=cisco123
¼
Message of the Day (MOTD) Banner
Unauthorized Access is Highly Prohibited!
¼
VTY
Enable SSH and Disable Telnet.
½
Encrypt the clear text passwords
Use the correct command to encrypt clear text passwords.
¼
Create the required VLANs.
Use the information provided to create the VLANs.
¼
Assign the management IP address.
Assign the IP Address just before the last valid IP Address on the Native&Management VLAN. VLAN 999 is the Native VLAN.
¼
Enable the 802.1Q Trunk ports.
Use the correct switchport command to set the Trunk port.
¼
Configure all other ports as access ports.
Use the interface range command.
¼
Assign F0/3 to the correct VLAN as per the diagram.
See the network diagram you drew for part 1.
¼
Shutdown all unused ports.
Disable all unused ports in software.
¼
Task 2: Configure SW2. (3.5 points possible)
Configuration Task
Required Information
Points
Switch name
SW2
¼
Secret Password
Netw204
¼
Disable DNS lookup
¼
Username and Password
User= Admin1, Password=cisco123
¼
Message of the Day (MOTD) Banner
Unauthorized Access is Highly Prohibited!
¼
VTY
Enable SSH and Disable Telnet.
½
Encrypt the clear text passwords
Use the correct command to encrypt clear text passwords.
¼
Create the required VLANs.
Use the information provided to create the VLANs.
¼
Assign the management IP address.
Assign the IP Address just before the last valid IP Address on the Native&Management VLAN. VLAN 999 is the Native VLAN.
¼
Enable the 802.1Q Trunk ports.
Use the correct switchport command to set the Trunk port.
¼
Configure all other ports as access ports.
Use the interface range command.
¼
Assign F0/3 to the correct VLAN as per the diagram.
See the network diagram you drew for part 1.
¼
Shutdown all unused ports.
Disable all unused ports in software.
¼
Task 3: Configure the NY Router. (6 points)
Configuration Item or Task
Required Information
Points
Configure 802.1Q subinterface .15 on G0/1
Description Executive LAN
Assign VLAN 15.
Assign the last valid IP address to this interface.
½
Configure 802.1Q subinterface .25 on G0/1
Description Engineering LAN
Assign VLAN 25.
Assign the last valid IP address to this interface.
½
Configure 802.1Q subinterface .35 on G0/1
Description Services LAN
Assign VLAN 35.
Assign the first available address to this interface.
½
Configure 802.1Q subinterface .999 on G0/1
Description Native&Management LAN
Assign VLAN 999.
Assign the last valid IP address to this interface.
½
Activate Interface G0/1
Bring up interfaces
½
OSPF Process ID
204
½
Router ID
1.1.1.1
½
Advertise directly connected networks.
Use classless network addresses
Assign all directly connected networks to Area 0
½
Set all LAN interfaces as passive.
Type necessary commands to do so.
½
Change the default cost reference bandwidth to support Gigabit interface calculations.
1000
½
Set the serial interface bandwidth.
768 Kb/s
½
Adjust the metric cost of S0/0/0.
Cost: 7500
½
Task 4: Configure the IL Router. (4 points)
Configuration Task
Required Information
Points
Assign IP addresses to appropriate interfaces including Loopback and serial interfaces.
½
Activate the nonLoopback interfaces.
½
OSPF Process ID
204
½
Router ID
2.2.2.2
½
Advertise directly connected networks.
Use classless network addresses.
Assign interfaces to Area 0.
Use a single summary address for the LAN (loopback) interfaces.
½
Set all LAN (Loopback) interfaces as passive.
½
Change the default cost reference bandwidth to support Gigabit interface calculations.
1000
½
Set the serial interface bandwidth.
256 Kb/s
½
Note: You will probably notice that all the Loopback IP addresses show up as /32. To change that /32 to the real subnet mask of the Loopback interfaces you need to type the following command on each Loopback interface in the routers.
Interface Loopback 1
ip ospf network point-to-point
Task 5: Configure the CA Router. (4 points)
Configuration Task
Required Information
Points
Assign IP addresses to appropriate interfaces including Loopback and serial interfaces.
½
Activate the nonLoopback interfaces.
½
OSPF Process ID
204
½
Router ID
3.3.3.3
½
Advertise directly connected networks.
Use classless network addresses.
Assign interfaces to Area 0.
Use a single summary address for the LAN (loopback) interfaces.
½
Set all LAN (Loopback) interfaces as passive.
½
Change the default cost reference bandwidth to support Gigabit interface calculations.
1000
½
Set the serial interface bandwidth.
256 Kb/s
½
Task 6: Verify OSPF Configuration (6 points)
Question
Points
Type the command that displays all connected OSPFv2 routers. Capture the output for your project and explains what you see.
1
Type the command that displays the OSPF process ID, router ID, routing networks, address summarization, and passive interfaces configured on a router. Capture the output for your project and explain what you see.
1
What command displays only OSPF routes?
1
What command displays detail information about the OSPF interfaces, including the authentication method?
1
What command displays the OSPF link states types?
1
What command displays the OSPF database?
1
Task 7: Summarize the output of the commands used in Task 6. How can you tell that the network is working correctly? (3 points)
Configuration Task
Required Information
Points
Switch name
SW1
¼
Secret Password
Netw204
¼
Disable DNS lookup
¼
Username and Password
User= Admin1, Password=cisco123
¼
Message of the Day (MOTD) Banner
Unauthorized Access is Highly Prohibited!
¼
VTY
Enable SSH and Disable Telnet.
½
Encrypt the clear text passwords
Use the correct command to encrypt clear text passwords.
¼
Create the required VLANs.
Use the information provided to create the VLANs.
¼
Assign the management IP address.
Assign the IP Address just before the last valid IP Address on the Native&Management VLAN. VLAN 999 is the Native VLAN.
¼
Enable the 802.1Q Trunk ports.
Use the correct switchport command to set the Trunk port.
¼
Configure all other ports as access ports.
Use the interface range command.
¼
Assign F0/3 to the correct VLAN as per the diagram.
See the network diagram you drew for part 1.
¼
Shutdown all unused ports.
Disable all unused ports in software.
¼
Explanation / Answer
This questions has lot of sub parts. Please post 3-4 more questions for the same. I am solving the first one.
set system name sw1
password Netw204
configure terminal
no ip domain-lookup
username Admin1 password cisco123
banner motd #
Unauthorized Access is Highly Prohibited! #
vty 04
service password-encryption