Examine the network and the cost table carefully in order to determine the activ

ID: 470921 • Letter: E

Question

Examine the network and the cost table carefully in order to determine the activity that must be crashed in order to reduce the project duration by a week.  According to you the activity that should be crashed is: Answer            

                            a.            H                             b.            E                             c.            F                             d.            D                             e.            G                             f.            A                             g.            C                             h.            B



Examine the network and the cost table carefully in order to determine the activity that must be crashed in order to reduce the project duration by a week. According to you the activity that should be crashed is: Answer

Explanation / Answer


d. D