Examine the network and the cost table carefully in order to determine the activity that must be crashed in order to reduce the project duration by a week. According to you the activity that should be crashed is: Answer
a. H b. E c. F d. D e. G f. A g. C h. BExamine the network and the cost table carefully in order to determine the activity that must be crashed in order to reduce the project duration by a week. According to you the activity that should be crashed is: Answer
Explanation / Answer