1. Consider the following project. (20 points)
Activity
Immediate Predecessor
Activity Time (days)
A
--
3
B
--
4
C
A
4
D
A
6
E
B
5
F
C,D
4
G
E,F
7
a.What is the critical path?
b. What is the slack time for activity C.
c.What is the latest finish time for activity F?
Activity
Immediate Predecessor
Activity Time (days)
A
--
3
B
--
4
C
A
4
D
A
6
E
B
5
F
C,D
4
G
E,F
7
Explanation / Answer
a. the critical path is- A-D-F-G, and the total duration to compelte the project is- 20
B. slack time for activity C is 2
c. latest finish time of actity F is 13