Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Need help with Q 4,5,6. B&W; Systems B &W; Systems design and distribute a varie

ID: 465666 • Letter: N

Question

Need help with Q 4,5,6.

B&W; Systems B &W; Systems design and distribute a variety of management software products through the Internet and retail outlets like Best Buy. The company is current considering the development of an Internet based forecasting system. This system is designed specifically for the new start-up and small business owner. The project manager, after consulting with the technical staff and reviewing historical efforts, has developed the task descriptions, time estimates and immediate predecessor (IP) relations. This information is reported in Table 1. The project manager plans to use existing software components during the development phase as a means of keeping project costs and overall timeframe within bounds. Nevertheless, multiple task time estimates were formulated due, in part, to the inherent uncertainties associated with software development. Table 1 - Project Description and Time Estimates (weeks) Most Likel Task Most Optimistic Description I.P Most Pessimistic Requirements Market Assessment Design Development Testing Revising Documentation Quality Assurance Pricing Production Distribution 16 10 B,E C,E F,G,H.I H B&W;'s management team has established a 35-week completion time for this effort. A preliminary assessment by the project management indicates that some of the project tasks will need to be shortened to meet the management deadline of 35 weeks. According, the project manager has prepared a set of task crashing estimates that are highlighted in Table 2. Table 2 - Project Crash Data Normal Costs (S) 10000 20000 15000 45000 10000 15000 20000 10000 5000 40000 15000 Crash Costs (S 10000 25000 30000 65000 20000 18000 30000 15000 5000 50000 25000 Task Crash Time (weeks)

Explanation / Answer

Activity

Preceding activity

Optimistic time

Most Likely time

Pessimestic tie

Expected time

Variance

o

m

p

te =(o+4m+p)/6

*

A

-

2

3

4

3.00

0.1111

B

A

4

7

10

7.00

1.0000

C

A

5

6

9

6.33

0.4444

D

C

6

7

16

8.33

2.7778

E

D

7

9

10

8.83

0.2500

F

B,E

4

5

6

5.00

0.1111

G

D

3

6

10

6.17

1.3611

H

C, E

2

4

7

4.17

0.6944

I

B

2

2

2

2.00

0.0000

J

F, G, H, I

3

4

14

5.50

3.3611

K

J

2

3

4

3.00

0.1111

Activity

On Critical Path

Average Time

Earliest Start

Earliest Finish

Latest Start

Latest Finish

Total Slack

Activity Variance

Critical Path Variance

A

y

3.00

0.00

3.00

0.00

3.00

0.00

0.2500

0.2500

B

N

7.00

3.00

10.00

19.50

26.50

16.50

0.1111

C

y

6.33

3.00

9.33

3.00

9.33

0.00

0.6944

0.6944

D

y

8.33

9.33

17.67

9.33

17.67

0.00

0.1111

0.1111

E

y

8.83

17.67

26.50

17.67

26.50

0.00

0.2500

0.2500

F

y

5.00

26.50

31.50

26.50

31.50

0.00

0.1111

0.1111

G

N

6.17

17.67

23.83

25.33

31.50

7.67

1.0000

H

N

4.17

26.50

30.67

27.33

31.50

0.83

0.4444

I

N

2.00

10.00

12.00

29.50

31.50

19.50

0.2500

J

y

5.50

31.50

37.00

31.50

37.00

0.00

0.1111

0.1111

K

y

3.00

37.00

40.00

37.00

40.00

0.00

0.1111

0.1111

Length of Project

40.00

Project Varience

1.6389

Project S.D.

1.2802

Mean Length of Project

40

Critical Path

A-C-D-E-F-J-K

Activity

Duration

NC

CT

CC

Crashing duration

Crashing cost per week

A

3.0

10000

3

10000

0

0

B

7.0

20000

6

25000

1

5000

C

6.3

15000

5

30000

1

11250

D

8.3

45000

6

65000

2

8571

E

8.8

10000

8

20000

1

12000

F

5.0

15000

4

18000

1

3000

G

6.2

20000

4

30000

2

4615

H

4.2

10000

3

15000

1

4286

I

2.0

5000

2

5000

0

0

J

5.5

40000

5

50000

1

20000

K

3.0

15000

2

25000

1

10000

4.

For reducing the project duration to 35 weeks, the activities to crashed and their crashing cost are listed below:

Activity

On Critical Path

Average Time

Earliest Start

Earliest Finish

Latest Start

Latest Finish

Total Slack

A

y

3.00

0.00

3.00

0.00

3.00

0.00

B

n

7.00

3.00

10.00

16.66

23.66

13.66

C

y

5.33

3.00

8.33

3.00

8.33

0.00

D

y

6.33

8.33

14.66

8.33

14.66

0.00

E

y

8.83

14.66

23.49

14.66

23.49

0.00

F

n

4.00

23.49

27.49

23.66

27.66

0.17

G

n

6.17

14.66

20.83

21.50

27.66

6.84

H

y

4.17

23.49

27.66

23.49

27.66

0.00

I

n

2.00

10.00

12.00

25.66

27.66

15.66

J

y

5.50

27.66

33.16

27.66

33.16

0.00

K

y

2.00

33.16

35.16

33.16

35.16

0.00

Length of Project

35.16

Still the critical path is A-C-D-E-F-J-K

Activities to be crashed

Additional Cost

F by 1 week

3000

D by 2 weeks

20000

K by 1 week

10000

C by 1 week

15000

Total Additional cost = $48,000

5.

As the B is non-critical activity increase in the duration to 9 weeks does not change the critical path.

6.

If the duration of activity D is reduced to 7 weeks, than the crashing cost will reduce.

Activity

Preceding activity

Optimistic time

Most Likely time

Pessimestic tie

Expected time

Variance

o

m

p

te =(o+4m+p)/6

*

A

-

2

3

4

3.00

0.1111

B

A

4

7

10

7.00

1.0000

C

A

5

6

9

6.33

0.4444

D

C

6

7

16

8.33

2.7778

E

D

7

9

10

8.83

0.2500

F

B,E

4

5

6

5.00

0.1111

G

D

3

6

10

6.17

1.3611

H

C, E

2

4

7

4.17

0.6944

I

B

2

2

2

2.00

0.0000

J

F, G, H, I

3

4

14

5.50

3.3611

K

J

2

3

4

3.00

0.1111

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote