The project proposal conveys which of the following to senior management?

1) It defines the business problem, lists the major profit areas of the business, and lists the social responsibility attributes.

2)It defines the business problem, sets project priorities, and sets long-range planning.

3) It sets project priorities, lists major deliverables, describes major quality issues, and lists the requirements for procuring resources and equipment.

4) It defines the business problem, lists the major deliverables, and describes the major risks to the organization.

Explanation / Answer

Ans=option 4

It defines the business problem, lists the major deliverables, and describes the major risks to the organization