Please show all work. Partial Answer Key: 3. Average flow time: SPT = 16, EDD =

ID: 464339 • Letter: P

Question

Please show all work.

Partial Answer Key:

3. Average flow time: SPT = 16, EDD = 17.333, CR = 20.167

The following jobs are waiting to be processed at the machine center. They are ready to be scheduled today, which is day 20 (day 20 is a work day). Complete the following table. (Show your supporting calculations. Which dispatching rule has the best score for flow time? Which dispatching rule has the best score for utilization metric? Which dispatching rule has the best score for lateness? In other words, number of days till due date for job A = 25 - 20 + 1 = 6.

Explanation / Answer

Consider Starting Date is 20, thus job due date for activity A = Date job is due - Starting date + 1

Job

Processing time

Date job is due

Job Due date

A

5

25

6

B

3

30

11

C

4

32

13

D

6

28

9

E

8

34

15

F

6

32

13

Shortest Processing Time (SPT) priority rule:

According to SPT rule the jobs are sequenced according to the processing time, the highest priority is assigned to job with shortest processing time.

Job Sequence by SPT: B-C-A-D-F-E

SPT Rule

Job Sequence

Processing time

Work Begins

Flow Time

Job Due date

Job Lateness

a

b

c = a +b

d

e

B

3

0

3

11

0

C

4

3

7

13

0

A

5

7

12

6

6

D

6

12

18

9

9

F

6

18

24

13

11

E

8

24

32

15

17

Total

32

64

96

43

Average

10.67

16

7.17

Measure of effectiveness of Priority Rule:

a. Average flow time = (total flow time/number of jobs)

Average flow time by SPT rule = 96/5 = 16

b. Utilization metric = Total processing time/total flow time

Utilization metric by SPT rule= 32/96 =33.33%

c. Average number of jobs in system = Total Flow time/Total Processing time

Average number of jobs in system by SPT rule = 96/32 = 3 jobs

d. Average job lateness = Total job lateness/number of jobs

Average job lateness by SPT rule = 43/5 = 7.17

Earliest Due Date (EDD) Priority Rule:

According to EDD rule the jobs are sequenced according to the job due date, the highest priority is assigned to job with earliest due date.

Job Sequence: A-D-B-C-F-E

EDD Rule

Job Sequence

Processing time

Work Begins

Flow Time

Job Due date

Job Lateness

a

b

c = a +b

d

e

A

5

0

5

6

0

D

6

5

11

9

2

B

3

11

14

11

0

C

4

14

18

13

0

F

6

18

24

13

11

E

8

24

32

15

17

Total

32

72

104

67

30

Average

12.00

17.33

11.17

5.00

Measure of effectiveness of Priority Rule:

a. Average flow time = (total flow time/number of jobs)

Average flow time by EDD rule = 104/5 = 17.33

b. Utilization metric = Total processing time/total flow time

Utilization metric by EDD rule= 32/104 =30.76%

c. Average number of jobs in system = Total Flow time/Total Processing time

Average number of jobs in system by EDD rule = 104/32 = 3.25 jobs

D*. Average job lateness = Total job lateness/number of jobs

Average job lateness by EDD rule = 30/5 = 5.00

Critical ratio Priority rule:

Critical ratio (CR) is computed as follows:

CR = (Due date –current time)/Processing time

Job

Processing time

Date job is due

Current Time

CR

Priority order

A

5

25

20

1

1

B

3

30

20

3.33

6

C

4

32

20

3

5

D

6

28

20

1.33

2

E

8

34

20

1.75

3

F

6

32

20

2

4

According to CR rule, the highest priority is given to job with lowest CR.

Sequence: A-D-E-F-C-B

CR Rule

Job Sequence

Processing time

Work Begins

Flow Time

Job Due date

Job Lateness

A

b

c = a +b

d

e

A

5

0

5

6

0

D

6

5

11

9

2

E

8

11

19

15

4

F

6

19

25

13

12

C

4

25

29

13

0

B

3

29

32

11

0

Total

32

89

121

67

18

Average

14.83

20.17

11.17

3.00

Measure of effectiveness of Priority Rule:

a. Average completion time = (total flow time/number of jobs)

Average completion time by CR rule = 121/5 = 20.17

b. Utilization metric = Total processing time/total flow time

Utilization metric by CR rule= 32/121 =26.44%

c. Average number of jobs in system = Total Flow time/Total Processing time

Average number of jobs in system by CR rule = 121/32 = 3.78 jobs

d. Average job lateness = Total job lateness/number of jobs

Average job lateness by CR rule = 18/5 = 3.00.

ANSWER

a.

SPT

EDD

CR

Average flow time

16

17.33

20.17

Average Lateness

7.17

5.00

3.00

Average no. of Jobs

3

3.25

3.78

Utilization

33.33%

30.76%

26.44%

b.

the lowest flow time is 16 days, SPT has the best score for flow time.

c.

The highest score for utilization metric is for sequencing by SPT rule. Thus, SPT rule has best score for utilization metric.

d.

Lowest average lateness is 3.00, CR has best score for lateness.

Job

Processing time

Date job is due

Job Due date

A

5

25

6

B

3

30

11

C

4

32

13

D

6

28

9

E

8

34

15

F

6

32

13