Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Develop a complete net material requirements plan for the production of followin

ID: 463133 • Letter: D

Question

Develop a complete net material requirements plan for the production of following MPS and prepare the “exceptions” report. Must be achieved without using excel, a partial solution is avaliable for your assistance, solve for total cost.

L-4-L

EOQ

POQ

Total cost =

2475.00

3704.05

2325.00

Master production schedule

Week:

1

2

3

4

5

6

MPS for A

200

100

200

200

MPS for B

200

80

100

80

Data:

Item

Lead time

Available

Scheduled Receipts

C

2

750

400 in week #1, 300 in week #2

D

1

500

600 in week #1

E

3

2000

2000 in week #1, 2000 in week #2

Bill-of-Materials:

B

E1

D3

E2

Put the “exceptions” report here:

A

D2

E3

C3

E2

D3

E2


Item :

LT =

GR =

Week:

1

2

3

4

5

6

Gross requirement

Scheduled receipts

Projected on-hand

Net Requirement

Planned receipts

Planned order releases

Item :

LT =

GR =

Week:

1

2

3

4

5

6

Gross requirement

Scheduled receipts

Projected on-hand

Net Requirement

Planned receipts

Planned order releases

Item :

LT =

GR =

Week:

1

2

3

4

5

6

Gross requirement

Scheduled receipts

Projected on-hand

Net Requirement

Planned receipts

Planned order releases

Item :

LT =

GR =

Week:

1

2

3

4

5

6

Gross requirement

Scheduled receipts

Projected on-hand

Net Requirement

Planned receipts

Planned order releases

Given setup cost of $350 per setup and holding cost of $2.50 per unit per week, develop lot sizes (a) Lot-for-lot, (b) EOQ, and (c) POQ. Determine the total cost for each method. Use lead time of one week.

(a) Lot-for-lot

LT =

1

Week:

1

2

3

4

5

6

7

8

Gross requirement

100

110

120

140

110

120

130

150

Scheduled receipts

Projected on-hand

110

Net Requirement

Planned receipts

Planned order releases

Total ending inventory =

No. of setup =

Carrying cost =

Setup cost =

Total cost =

(b) EOQ

LT =

1

Week:

1

2

3

4

5

6

7

8

Gross requirement

100

110

120

140

110

120

130

150

Scheduled receipts

Projected on-hand

110

Net Requirement

Planned receipts

Planned order releases

Holding cost/week =

Setup cost/week =

Total cost/week =

Cost for 8 weeks =

(c) POQ

LT =

1

Week:

1

2

3

4

5

6

7

8

Gross requirement

100

110

120

140

110

120

130

150

Scheduled receipts

Projected on-hand

110

Net Requirement

Planned receipts

Planned order releases

Total ending inventory =

No. of setup =

Carrying cost =

Setup cost =

Total cost =

L-4-L

EOQ

POQ

Total cost =

2475.00

3704.05

2325.00

Explanation / Answer

Part 1

Period

-1

1

2

3

4

5

6

MPS for A

200

100

200

200

MPS for B

200

80

100

80

Item: C
OH = 750
LT = 2
Q =L4L

-1

1

2

3

4

5

6

Gross Req.

600

300

600

0

0

600

3 for A

Scheduled receipts

400

300

Projected-on-hand

750

550

550

150

150

150

0

Net Requirement

0

0

0

0

0

450

Planned order Receipts

450

Planned order releases

450

Item: D
OH = 500
LT = 1
Q = L4L

-1

1

2

3

4

5

6

Gross Req.

400

200

400

0

0

400

2 For A

0

0

0

1350

0

0

3 For C

0

600

240

300

240

0

3 For B

Scheduled receipts

600

0

0

0

0

0

Projected-on-hand

500

700

0

0

0

0

0

Net Requirement

0

100

640

1650

240

400

Planned order Receipts

0

100

640

1650

240

400

Planned order releases

100

640

1650

240

400

0

Item: E
OH = 2000
LT = 3
Q =L4L

-1

1

2

3

4

5

6

Gross Req.

200

1280

3300

480

800

0

2 for D

600

300

600

0

0

600

3 for A

0

200

80

100

80

0

1 for B

Scheduled receipts

2000

2000

0

0

0

0

Projected-on-hand

2000

3200

3420

0

0

0

Net Requirement

0

0

560

480

800

600

Planned order Receipts

0

0

560

480

800

600

Planned order releases

560

480

800

600

0

0

0

Part 2

Given setup cost of $350 per setup and holding cost of $2.50 per unit per week, develop lot sizes (a) Lot-for-lot, (b) EOQ, and (c) POQ. Determine the total cost for each method. Use lead time of one week.

S = Setup cost = $350

H = Holding cost = $2.5 per unit per week

a) Lot-for-lot

LT =

1

Week:

1

2

3

4

5

6

7

8

Gross requirement

100

110

120

140

110

120

130

150

Scheduled receipts

0

Projected on-hand

110

10

0

0

0

0

0

0

0

Net Requirement

0

100

120

140

110

120

130

150

Planned receipts

0

100

120

140

110

120

130

150

Planned order releases

100

120

140

110

120

130

150

0

Total ending inventory =

10

No. of setup =

7

Carrying cost =

$2.5 x 10 = $25.00

Setup cost =

$350 x 7 = $2,450.00

Total cost =

$25 + $2450 = $2,475.00

Average demand = A = (100+110+120+140+110+120+130+150)/8 = 122.5 units

EOQ = Q* = sqrt{ rac{2*A*S}{H}}

Q* = sqrt{ rac{2*122.5*350}{2.5}}

Q* = 185

EOQ

Q = 185

LT =

1

Week:

1

2

3

4

5

6

7

8

Gross requirement

100

110

120

140

110

120

130

150

Scheduled receipts

0

Projected on-hand

110

10

85

150

10

85

150

20

55

Net Requirement

0

100

35

0

100

35

0

130

Planned receipts

0

185

185

0

185

185

0

185

Planned order releases

185

185

0

185

185

0

185

0

Total ending inventory =

565

No. of setup =

5

Carrying cost =

$2.65 x 565 = $1,412.50

Setup cost =

$350 x 5 = $1,750.00

Total cost =

$3,162.50

POQ = EOQ/Average Demand = 185/122.5 = 1.51 ~ 2 weeks

POQ

2 weeks

LT =

1

Week:

1

2

3

4

5

6

7

8

Gross requirement

100

110

120

140

110

120

130

150

Scheduled receipts

0

Projected on-hand

110

10

120

0

110

0

130

0

0

Net Requirement

0

100

0

140

0

120

0

150

Planned receipts

0

220

0

250

0

250

0

150

Planned order releases

220

0

250

0

250

0

150

0

Total ending inventory =

370

No. of setup =

4

Carrying cost =

$2.5 x 370 = $925.00

Setup cost =

$350 x 4 = $1,400.00

Total cost =

$2,325.00

Period

-1

1

2

3

4

5

6

MPS for A

200

100

200

200

MPS for B

200

80

100

80

Item: C
OH = 750
LT = 2
Q =L4L

-1

1

2

3

4

5

6

Gross Req.

600

300

600

0

0

600

3 for A

Scheduled receipts

400

300

Projected-on-hand

750

550

550

150

150

150

0

Net Requirement

0

0

0

0

0

450

Planned order Receipts

450

Planned order releases

450

Item: D
OH = 500
LT = 1
Q = L4L

-1

1

2

3

4

5

6

Gross Req.

400

200

400

0

0

400

2 For A

0

0

0

1350

0

0

3 For C

0

600

240

300

240

0

3 For B

Scheduled receipts

600

0

0

0

0

0

Projected-on-hand

500

700

0

0

0

0

0

Net Requirement

0

100

640

1650

240

400

Planned order Receipts

0

100

640

1650

240

400

Planned order releases

100

640

1650

240

400

0

Item: E
OH = 2000
LT = 3
Q =L4L

-1

1

2

3

4

5

6

Gross Req.

200

1280

3300

480

800

0

2 for D

600

300

600

0

0

600

3 for A

0

200

80

100

80

0

1 for B

Scheduled receipts

2000

2000

0

0

0

0

Projected-on-hand

2000

3200

3420

0

0

0

Net Requirement

0

0

560

480

800

600

Planned order Receipts

0

0

560

480

800

600

Planned order releases

560

480

800

600

0

0

0