Looking for not only the solution but an explanation behind the solution for the
ID: 462608 • Letter: L
Question
Looking for not only the solution but an explanation behind the solution for the following:
A company is working on a project with a budget of $1000. The planned value as of today is $400. The project is 30% complete and 60% of the budget has been spent. If the company continues to spend at the same rate, the project cost will be:
$1000
$800
$600
$400
Every time I work this problem I get $1,400, but that isn't one of the options. Any ideas?
1.$1000
2.$800
3.$600
4.$400
Every time I work this problem I get $1,400, but that isn't one of the options. Any ideas?
Explanation / Answer
2) $ 600
The total Budget estimate was $ 1000. The planned estimate for 30% of the work is $400 , which means for 70% of the remaining work , your plan is to spend $600.
But the actual spending is 60% of the budget = 60% of 400 = $240
Actual spending ratio = 60%
Since required amount for completing the reamining work = 60% of 600 = $360
So the total expense for completing the project = $240+$360 = $600