You are the project manager for your company, Mark Manufacturers. Your company has a large client that has requested a special component be created for one of their test engines. Your organization agrees and creates a standard contract with the customer, and your manager assigns you to manage this project. The project was launched because of which one of the following?
A. A customer request
B. A change in the technology your customer is creating
C. A legal requirement (contractual)
D. An organizational need
Explanation / Answer
A. A customer request
Customer has requested for a special component ( apart from normal business). Thus it must be critical for the customer point of view, Thus a project is created to perform it on the stipulated time period and with more care and attention.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.