Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Tabard Industries forecasted the following demand for one of its most profitable

ID: 461455 • Letter: T

Question

Tabard Industries forecasted the following demand for one of its most profitable products for the next 8 weeks: 100, 100, 100, 80, 80, 80, 60, and 60 units. The booked customer orders for this product, starting in week 1 are: 110, 80, 50, 40, 30, 10, 0, and 0 units. The current on-hand inventory is 250 units, the order quantity is 200 units, and the lead time is one week. a. Develop a MPS for this product. (Enter your responses as whole numbers. A response of "0" is equivalent to being not applicable.)

Explanation / Answer

To obtain the MPS order following steps is repeated for each week.

1.calculate Gross requirement for each week = Forecast (1) + Customer orders (2)

2. Obtain the opening inv. which is equal to projected on-hand of previous period. For first week opening inventory = 200 units.

3. Calculate difference or actual requirement by subtracting (3) from (4). If the difference is positive then don’t place an order for that week. If the difference is negative then place the order of 200 units for the given week as per order policy. For example difference for week 2 is -140, so place order of 200 units. MPS quantity for week 2 is 200 units.

4. Now calculate projected on-hand or ending inventory of the week by adding difference (5) and MPS quantity (7). Or it can be calculated as follows:

Projected on-hand = MPS quantity + Opening inv. – Gross requirement

Week

1

2

3

4

5

6

7

8

1

Forecast

100

100

100

80

80

80

60

60

2

Customer orders

110

80

50

40

30

10

0

0

3

gross req. (1+2)

210

180

150

120

110

90

60

60

4

opening inv.

250

40

60

110

190

80

190

130

5

Difference (4-3)

40

-140

-90

-10

80

-10

130

70

6

Projected on-hand

(7+5) or (7+4-3)

40

60

110

190

80

190

130

70

7

MPS quantity

0

200

200

200

0

200

0

0

Week

1

2

3

4

5

6

7

8

1

Forecast

100

100

100

80

80

80

60

60

2

Customer orders

110

80

50

40

30

10

0

0

3

gross req. (1+2)

210

180

150

120

110

90

60

60

4

opening inv.

250

40

60

110

190

80

190

130

5

Difference (4-3)

40

-140

-90

-10

80

-10

130

70

6

Projected on-hand

(7+5) or (7+4-3)

40

60

110

190

80

190

130

70

7

MPS quantity

0

200

200

200

0

200

0

0