Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

P Do Homework Brody Horning Google Chrome https:// 3584009978 questionld 18 flus

ID: 461131 • Letter: P

Question

P Do Homework Brody Horning Google Chrome https:// 3584009978 questionld 18 flushed false&cld; 3889895&centerwin; yes Brody Horning 6/13/16 11:41 AM Homework: HW10 Chapters 7, 7S; Process Strat, Cap Plan Overview 16 (1 Problem S7.11 16 of 17 complete Exercise Score: 0 of 2 pts Assignment Score: 78.79% (17.33 of 22 pts) The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel before proceeding to station 2. Capacity: 30 units/hr Station 1 Machine A Station 2 Station 3 Station 1 Capacity Capacity Machine B 6 units/h 12 units/hr Capacity: 30 units/hr a The bottleneck time of the system is minutes per unit (enter your response as a whole number) Enter your answer in the answer box, then click Check Answer. 3 parts remaining Clear All Check Answer Save 11:41 AM 6/13/2016

Explanation / Answer

The bottleneck means slowest station or longest time taking station that is station-2 in this case.

The bottleneck time = 60/production rate

The bottleneck time = 60/6

The bottleneck time = 10 minutes per unit.