The Oxford Copy Shop and Typing Pool is a local copy shop that produces course p
ID: 459130 • Letter: T
Question
The Oxford Copy Shop and Typing Pool is a local copy shop that produces course packets. Professors take copies of handout and other course-related materials to the Copy Shop, which duplicates them and sells them to students. The jobs are due at the end of the day on the Due Dates that are provided. It is now the beginning of Day 6 and the store has the following jobs on hand:
Job
Day Brought to Shop
Processing Time (Days)
Due at the end of Day ___
BA 426
1
4
14
MGT 302
2
2
9
MKT 291
3
8
14
ACC 321
4
6
22
MIS 235
5
7
20
You are asked to schedule and evaluate several sequencing rules. You are ready to schedule these six jobs. They are all ready to be processed.
a) Determine the sequence of jobs using the following rules:
Critical ratio rule (CR) – using the definition of the critical ratio rule that we used on our assignment
Longest Processing Time (LPT)
b) Prioritize the rules used in a) based on average flow time measured from now.
c) Prioritize the rules used in a) based on average lateness with no credit for completing any test early (in other words, the late time would be set at zero if a job is early).
d) Prioritize the rules used in a) based on average early time with no penalty for completing any test late (in other words, the early time would be set at zero if a job is late).
Job
Day Brought to Shop
Processing Time (Days)
Due at the end of Day ___
BA 426
1
4
14
MGT 302
2
2
9
MKT 291
3
8
14
ACC 321
4
6
22
MIS 235
5
7
20
Explanation / Answer
Critical ratio rule = time remaining / work days remaining
Job wise critical ratio:
i) BA 426
Remaining time = 9 days
Workdays remaining = 4 days
Critical ratio= 9/4
= 2.25
ii) MGT 302
Remaining time = 4 days
Workdays remaining = 2 days
Critical ratio= 4/2
= 2
iii) MKT 291
Remaining time = 9 days
Workdays remaining = 8 days
Critical ratio= 9/8
= 1.125
iv) ACC 321
Remaining time = 17 days
Workdays remaining = 6 days
Critical ratio= 17/6
= 2.83
v) MIS 235
Remaining time = 15 days
Workdays remaining = 7 days
Critical ratio= 15/7
= 2.14
The priority order of job is performed from smaller to larger value of critical value.therefore sequence of job is
MKT 291 -> MGT 302 -> MIS 235 -> BA 426 -> ACC 321
Based on Longest processing time
Sequence of job is
MKT 291 -> MIS 235 -> ACC 321 -> BA 426 -> MGT 302
b) On the basis of above table, Comparison of Rule based on average flow:
CR = 16.6
LPT = 19.2
CR will have higher priority
c) On the basis of above table,Comparison of Rule based on average Lateness:
CR = 5.8
LPT = 8.4
CR will have higher priority
CR Proc. time Flow time Time to Due Lateness (Flow Time- Due date) MKT 291 8 8 9 -1 MGT 302 2 10 (8+ 2) 4 6 MIS 235 7 17 (10 +7) 15 2 BA 426 4 21 9 12 ACC 321 6 27 17 10 Total 27 83 54 29 Mean 16.6 5.8Related Questions