question 12 All of the following methods have proven to be useful techniques to
ID: 458306 • Letter: Q
Question
question 12
All of the following methods have proven to be useful techniques to help project teams identify the risks that might impact the project EXCEPT:
reviewing project documents
documenting lessons learned
interviewing stakeholders
brainstorming among team members and subject matter experts
4 points
Question 13
The process of reviewing all change requests, approving changes, and managing changes to deliverables, organizational process assets, project documents and project management plan; and communicating their disposition, is known as:
perform project monitoring.
variance analysis and control.
perform integrated change control.
configuration management
4 points
Question 14
On some projects, some deliverables remain incomplete at project close-out. Activities that are not complete should be itemized, and responsibility for each should be clearly identified.
True
False
4 points
Question 15
Change control includes which of the following activities?
identifying, documenting, approving or rejecting, modifications to documents, deliverables, or baselines
brainstorming, selecting and implementing new ideas
recruiting, selecting and training new team members
identifying and implementing changes to the project charter
4 points
Question 16
All of the following are among the benefits realized as a consequence of developing a cost management plan EXCEPT:
It shows how to develop and share relevant, accurate and timely information that stakeholders can use to make intelligent and ethical decisions.
It documents how the business case should be created
It helps stakeholders to focus on schedule and performance as well as cost.
It provides feedback that shows how the project’s success is related to business objectives.
4 points
Question 17
Some project sponsors will only approve a project charter if it includes and reflects lessons learned from other recently completed projects.
True
False
4 points
Question 18
Which of the following is among the widely accepted project team success factors?
effective communication including performance feedback
emphasis on the quality of project deliverables, without regard to cost
extreme risk taking strategies to maximize project gains
use of coercion to resolve conflicts and problems
reviewing project documents
documenting lessons learned
interviewing stakeholders
brainstorming among team members and subject matter experts
Explanation / Answer
Q 12 - documenting lessons learned
Q13 - perform integrated change control
Q14 - True
Q15 - identifying, documenting, approving or rejecting, modifications to documents, deliverables, or baselines