Which of the following is true of the triple constraint in projects? The time co

ID: 458100 • Letter: W

Question

Which of the following is true of the triple constraint in projects?

The time constraint is the most critical of the three constraints in projects.

The three fundamentals that are known to constrain projects are insulated from each other.

Changes in one fundamental constraint force changes in the other constraints as well.

Cost constraints take precedence over time and scope constraints in all projects.

The time constraint is the most critical of the three constraints in projects.

The three fundamentals that are known to constrain projects are insulated from each other.

Changes in one fundamental constraint force changes in the other constraints as well.

Cost constraints take precedence over time and scope constraints in all projects.

Explanation / Answer

Changes in one fundamental constraint force changes in the other constraints as well.