An order for 200 of a product is processed on work centres A, B, and C. The setu
ID: 456697 • Letter: A
Question
An order for 200 of a product is processed on work centres A, B, and C. The setup time on A is 75 minutes, and run time is 4 minutes per piece. The setup time on B is 110 minutes, and run time is 3 minutes per piece. The setup time on C is 60 minutes, and run time is 5 minutes per piece. Wait time between A and B is 5 hours. Wait time between B and C is 8 minutes. The move time between A and B is 35 minutes. The move time between B and C is 25 minutes. Wait time after operation C is 5 hours, and the move time into stores is 7 hours. Queue at work center A is 10 hours, at B is 15 hours, and C is 12 hours. Calculate the total manufacturing lead time for the order.
Explanation / Answer
An order for 200 of a product is processed on work centers A, B, and C. The setup time on A is 75 minutes, and run time is 4 minutes per piece. The setup time on B is 110 minutes, and run time is 3 minutes per piece. The setup time on C is 60 minutes, and run time is 5 minutes per piece. Wait time between A and B is 5 hours. Wait time between B and C is 8 minutes. The move time between A and B is 35 minutes. The move time between B and C is 25 minutes. Wait time after operation C is 5 hours, and the move time into stores is 7 hours. Queue at work center A is 10 hours, at B is 15 hours, and C is 12 hours. Calculate the total manufacturing lead time for the order.
Answer :
Order = 200 of a product is processed on work centers
Work centeres = A, B, and C.
Setup time & Run Time
A = 75 minutes, and 4 minutes per piece.
B = 110 minutes, and 3 minutes per piece.
C = 60 minutes, and 5 minutes per piece.
Wait time between A and B is 5 hours.
Wait time between B and C is 8 minutes.
The move time between A and B is 35 minutes.
The move time between B and C is 25 minutes.
Wait time after operation C is 5 hours
move time into stores is 7 hours.
Queue at
work center A is 10 hours
at B is 15 hours
C is 12 hours.
Calculate the total manufacturing lead time for the order = ?
Total Manufacturing Lead time = 3565 min
In Hour In Min Set Up Time Center A 75 Queue at Work Center A 10 600 Work Center A Operation Time 4 Wait time A & B 5 300 Move time from A to B 35 Set Up Time Center B 110 Queue at Work Center B 15 900 Work Center B Operation Time 3 Wait time B & C 8 Move time from B to C 25 Set Up Time Center C 60 Queue at Work Center C 12 720 Work Center C Operation Time 5 Wait time C to stores 5 300 Move time from C to Stores 7 420 3565Related Questions