Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Suppose we had a project with only eight activities, as ilustrated in the next t

ID: 456634 • Letter: S

Question

Suppose we had a project with only eight activities, as ilustrated in the next table. The table also shows our calculated normal activity durations and costs and crashed durations and their costs. As a project manager, you have been asked to do full crashing.

Activity

Normal

Duration                 Cost

Crash

Duration                Cost

A

5 days

$ 1,000

3 days

$ 1,500

B

7 days

700

6 days

1,000

C

3 days

2,500

2 days

4,000

D

5 days

1,500

5 days

1,500

E

9 days

3,750

6 days

9,000

F

4 days

1,600

3 days

2,500

G

6 days

2,400

4 days

3,000

H

8 days

9,000

5 days

15,000

TOTAL COST=

22,450

$ 37,500

Activity

Normal

Duration                 Cost

Crash

Duration                Cost

A

5 days

$ 1,000

3 days

$ 1,500

B

7 days

700

6 days

1,000

C

3 days

2,500

2 days

4,000

D

5 days

1,500

5 days

1,500

E

9 days

3,750

6 days

9,000

F

4 days

1,600

3 days

2,500

G

6 days

2,400

4 days

3,000

H

8 days

9,000

5 days

15,000

TOTAL COST=

22,450

$ 37,500

Explanation / Answer

If all the eight activities are in a simple series, then the full crashing cost will be the sum total of the crash cost of all activities. In that the the project completion time is 34 days and total project cost is $ 37500

However, if the activites have predecessors, then we need to make AON (network) diagram, establish the critical path, and then crash the activities along the critical path. If there's predecessor to activities, please share that information, basis which I can provide the revised solution according to the precedence schedule.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote