Question 2 (1 point) ROP (reorder point)=expected demand during lead time+ cycle

ID: 455549 • Letter: Q

Question

Question 2 (1 point)

ROP (reorder point)=expected demand during lead time+ cycle Stock

Question 2 options:

Question 3 (1 point)

Raising the level of safety inventory provides higher levels of product availability and customer service

Question 3 options:

Average inventory is therefore cycle inventory minus safety inventory

Question 4 options:

Question 5 (1 point)

Cycle service level (CSL) is equal to the probability of not having a stockout in a replenishment cycle

Question 5 options:

Question 6 (1 point)

Safety stock increases risk of stockout during lead time

Question 6 options:

True False

Explanation / Answer

Q2-False

Q3-True

Q4-False It's Cycle inventory plus safety inventory

Q5-True

Q6 False