The data in Excel worksheet Q1 list processing time values for 40 samples of siz
ID: 453970 • Letter: T
Question
The data in Excel worksheet Q1 list processing time values for 40 samples of size 4 that were taken from Rapid Check Kiters, Inc.’s check processing firm over a 20-hour period
a.) Compute the mean and standard deviation of all 40 samples for the sample data.
b.) Calculate the control limits and construct the - and R charts, using the first 20 samples. Is the process under control at that point?
c.) Specifications for the process are 1.065 ±0.14. If the process is under control, calculate the capability indexes, Cpu, Cpl, Cp and Cpk. What do the indexes indicate?
The results of the initial 20 samples of size 4 are shown below.
Initial dataThe results of the initial 20 samples of size 4 are shown below.
Sample DATA 1 1.01 1.03 1.07 1.10 2 1.15 1.05 1.08 1.01 3 1.08 1.14 1.06 1.10 4 0.98 1.08 0.97 1.04 5 1.13 1.05 1.14 1.01 6 1.06 1.10 1.16 1.02 7 1.03 1.04 1.13 1.05 8 1.08 1.11 1.14 1.07 9 1.13 1.11 1.06 1.05 10 1.16 1.06 1.07 1.02 11 1.08 1.00 0.99 1.03 12 1.11 1.07 1.05 1.05 13 1.09 1.13 1.09 1.14 14 1.05 0.95 1.15 1.08 15 1.07 1.04 1.10 1.06 16 1.05 1.07 1.06 1.04 17 1.03 1.08 1.04 1.08 18 1.01 1.08 1.05 1.04 19 1.08 1.07 1.11 1.06 20 1.09 1.08 1.02 1.15Explanation / Answer
Sample DATA Mean (X Bar) R 1 1.01 1.03 1.07 1.1 1.05 0.09 2 1.15 1.05 1.08 1.01 1.07 0.14 3 1.08 1.14 1.06 1.1 1.10 0.08 4 0.98 1.08 0.97 1.04 1.02 0.11 5 1.13 1.05 1.14 1.01 1.08 0.13 6 1.06 1.1 1.16 1.02 1.09 0.14 7 1.03 1.04 1.13 1.05 1.06 0.1 8 1.08 1.11 1.14 1.07 1.10 0.07 9 1.13 1.11 1.06 1.05 1.09 0.08 10 1.16 1.06 1.07 1.02 1.08 0.14 11 1.08 1 0.99 1.03 1.03 0.09 12 1.11 1.07 1.05 1.05 1.07 0.06 13 1.09 1.13 1.09 1.14 1.11 0.05 14 1.05 0.95 1.15 1.08 1.06 0.2 15 1.07 1.04 1.1 1.06 1.07 0.06 16 1.05 1.07 1.06 1.04 1.06 0.03 17 1.03 1.08 1.04 1.08 1.06 0.05 18 1.01 1.08 1.05 1.04 1.05 0.07 19 1.08 1.07 1.11 1.06 1.08 0.05 20 1.09 1.08 1.02 1.15 1.09 0.13 Mean X double bar 1.07 0.09 R bar St. Dev. 0.02 X bar n 4 UCL X Double bar +A2 *R bar 1.137537 A2 0.729 LCL X Double bar - A2 *R bar 1.001214 D3 0 D4 2.282 R bar UCL D4 * R bar 0.213367 LCL D3 * R bar 0 The process is under control Specifications for the process are 1.065 ±0.14 upper specification 1.205 lower specification 0.925 mean 1.065 Cp = (upper specification - lower specification)/ 6 2.016546 Cpl(mean - lower specification)/3 0.00108 Cpu(upper specification - mean)/3) 0.00108 Cpk = min of { (mean - lower specification)/3, (upper specification - mean)/3)} 0.00108