Which of the following is NOT considered a project indirect cost? Supervision Co

ID: 453761 • Letter: W

Question

Which of the following is NOT considered a project indirect cost? Supervision Consultants Equipment Interest The project manager's salary Emily has recently learned that she needs to reduce the duration of her project meet an imposed deadline. She has calculated the crash cost per unit and knows the maximum units each activity can be reduced. What is the next step? Find the activity with the lowest crash cost Calculate the optimum cost-time point Calculate the crash point D. Identify the critical path I Find the activity with the highest crash cost Reducing project duration Involves crashing all activities to their crash point Can only be done when resources are not constrained. Is always more expensive. Tends to increase network sensitivity. Should be considered for all projects.

Explanation / Answer

22. C Equipment .

23. D. Identify the critical path. The activities along the critical path have to be reduced.

24. C. is always more exensive.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote