Which of the following best describes monetary assets, fixtures, stockholder equ

ID: 453745 • Letter: W

Question

Which of the following best describes monetary assets, fixtures, stockholder equity, and utility? Select one: a. Benefit b. Business Value c. Performance Metrics d. Project Justification Question

2 Which of the following is NOT one of the typical strategic reasons that projects are authorized, as stated by the PMBOK? Select one: a. Market Demand b. Customer Request c. Lack of Resources d. Legal Requirements

3.Programs are different than Projects in which one of these ways? Select one: a. Defined Objectives b. Large Scopes c. Changed is Controlled d. Timeliness is Success Question

4 The following is the primary function of the Project Management Office (PMO): Select one: a. Attend the Change Control Board (CCB) meetings b. Support project managers in a variety of ways c. Discipline project managers that go rogue d. Monitor external stakeholders Question

5 Which of the following is not a process group listed by the PMBOK? Select one: a. Closing b. Conducting c. Initiating d. Planning Question

6 The Product Life Cycle includes all BUT which one of the following stage: Select one: a. Maturity b. Decline c. Introduction d. Development Question

7 Which of the following is NOT a project? Select one: a. Expanding a road to include two lanes b. Processing Payroll c. Studying for the PMP exam d. Creating a user’s guide for trouble ticket systems Question

8 According to the PMBOK®, every project creates a unique product, service, or result. Select one: True False Question

9 A project manager is guaranteed of success if the project is completed on schedule and within budget. Select one: True False

10 PMBOK® defines a portfolio as a group of interrelated projects managed in a coordinated way to obtain benefits and control not available from managing them individually. Select one: True False

Explanation / Answer

1) b. Business value

2) c. lack of resources

3) a. defined objectives

4) b. support project manager..

5) b. Conducting

6) d. Development

7) b. Process payroll

8) true

9) False

10) false