The MRP gross requirements for item A are shown here for the next 10 weeks. Lead

ID: 453426 • Letter: T

Question

The MRP gross requirements for item A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $12. There is a carrying cost of $0.015 per unit per week. Beginning inventory is 80 units.
The MRP gross requirements for ltem A are shown here for the next 10 weeks. Lead time for A is three weeks and setup cost is $12. There is a carrying cost of $0.015 per unit per week. Beginning inventory is 80 units. WEEK 10 Gross requirements 2545 10 2070 70 20 50 195 70 12456 78 8 Use the least total cost and the least unit cost lot-sizing method to determine what quantity the first order should be released and for which period Quantity Ordered Period Least total cost (Click to select (Click to select Least unit cost eBook &Resources;

Explanation / Answer

the least total cost is at 4 to 6 units

at the same level the least unit cost also at 4 to 6 units