The Department of Transportation has found that a proposed highway project is no
ID: 452713 • Letter: T
Question
The Department of Transportation has found that a proposed highway project is not going to be completed before the end of the summer. They have asked the contractor to prepare cost figures to shorten the project by up to 6 weeks.
The following table shows the Crashing Costs for each activity. For example, if you needed to shorten Activity 1-2 by 1 week this would cost $12. If you needed to shorten the same activity by 2 weeks it would cost $16. Note: If an activity lists a cost of $---, then this activity cannot be any shorter.
Activity
First Week
Second Week
Third Week
1-2
$12
$16
$ ---
2-5
6
8
10
5-7
7
8
11
7-11
7
11
---
11-13
4
8
10
1-3
12
14
19
3-8
5
---
---
8-11
12
13
14
3-9
14
16
16
9-12
8
8
10
12-13
7
11
---
1-4
10
14
18
4-6
12
14
18
6-10
11
12
---
10-12
14
15
---
Note: For each week you are to include only the cost of shortening the activities in that particular week.
Save
Activity
First Week
Second Week
Third Week
1-2
$12
$16
$ ---
2-5
6
8
10
5-7
7
8
11
7-11
7
11
---
11-13
4
8
10
1-3
12
14
19
3-8
5
---
---
8-11
12
13
14
3-9
14
16
16
9-12
8
8
10
12-13
7
11
---
1-4
10
14
18
4-6
12
14
18
6-10
11
12
---
10-12
14
15
---
Explanation / Answer
Partial Answer
There are four paths in this project
1-2-5-7-11-13 = 34 weeks
1-3-8-11-13 = 32 weeks
1-3-9-12-13 = 35 weeks
1-4-6-10-12-13 = 35 weeks
So critical path having length of 35 weeks
Hence currently length of project is 35 Weeks
Need more information to resolve this question